Certification
 
 
   
 
 

Latest Projects
       Overview of Latest Projects

In addition to ongoing yearly maintenance contracts with various cement production plants, gas commission, and others;        UTS has performed numerous jobs in a considerable number of huge industrial projects in the UAE.

  1. Gulf Cement Company
          Ras Al Khaimah, U.A.E.
      Bauxite and Iron Ore conveying system
  • Fabrication, erection, blasting and painting of around 200 tons of steel structure, ducts, and chutes.
  • Erection more than 50 tons of equipment, and conveyors.
  • Modification of existing structure, around 15 tons.

 

  2. JBF RAK (Job in Progress)
          Al Hamra Free Zone, Ras Al Khaimah, U.A.E.
 
      PET Production Plant
  • Fabrication, erection, cleaning and testing of around 20 thousand inch meters of piping for Hot Oil, Compressed air, Cooling Water, Hot Water, Chilled Water, etc.
  • Fabrication and erection of over 150 tons of steel in hand railing and platforms.
  • Erection of around 100 tons of Stainless Steel Ducting..
  • Installation of around 8 thousand Sqm of thermal and cryogenic insulation on piping and ducts
JBF Project01 JBF Project02 JBF Project03 JBF Project04
JBF Project05 JBF Project06 JBF Project07 JBF Project08
JBF Project09 JBF Project10 JBF Project11 JBF Project12
 
  3. JBF RAK (Job in Progress)
          Al Hamra Free Zone, Ras Al Khaimah, U.A.E.
 
      PET Film Plant (Three Production Lines)
  • Fabrication and erection of over 220 tons of Stainless Steel Silos.
  • Fabrication and erection of around 650 tons of hot rolled steel structure.
  • Fabrication and erection of over 80 thousand inch meters of piping for Chilled Water, Hot Oil, Compressed Air, Chips Conveying System.
  • Installation of around 12 thousand Sqm of thermal and cryogenic insulation on piping and ducts.
  4. Guardian Zoujaj International
          Al Hamra Free Zone, Ras Al Khaimah, U.A.E.
 
      Float Glass Factory
  • Supply, fabrication, erection, cleaning and testing of LPG system.
  • Supply, fabrication, erection, cleaning and testing of over 15Klms of piping for LPG, Natural gas, Hydrogen, Nitrogen, Oxygen, Compressed air, water, etc.
  • Fabrication and erection of over 200 tons of steel in hand railing and platforms.
  • Erection of over 200 tons of equipment, in Pumps, Filters, Boilers, Skids, Compressors, Dryers, Vaporizers, etc.
  • Fabrication, installation and thermal insulation of hot gas ducting.
  5. Gulf Cement Company
        Ras Al Khaimah, U.A.E.
 
      New Kiln Project
  • Fabrication, erection, cleaning and testing of natural gas piping to kilns and pre-heater tower.
  • Fabrication and erection more than 250 tons of equipment and ducting for the de-dusting system and conveyors.
  • Installation of around 50 thousand Sqm of thermal insulation on ducting, filters, and cyclones.
  6. Gulf Cement Company
        Ras Al Khaimah, U.A.E.
 
      Coal Mill Project
  • Fabrication of over 700 tons of steel in structure, ducting, and equipment.
  • Fabrication and erection of over 100 tons of hand railing and platforms.
  • Supply and installation of thermal insulation on hot ducting and equipment.
  • Installation of pipe-work between coal mill and kilns.
  7. Ras Al Khaimah Cement Company
          Ras Al Khaimah, U.A.E.
  • Replacement of pre-heater exhaust duct.
  • Removal and reinstallation of refractory lining in pre-heater tower and kiln
  • Removal and replacement of raw mill plates.
  • Reparation of conveyor belt rollers.
 


 
 
© 2006 | Unimarine Technical Services | Part of Union Holding Company